What we learnt, and what went wrong
The analysis caught several problems before anything was printed, while they were still cheap to fix. These are the lessons we are taking into the build, and the troubles that taught them.
Weigh the airframe from the CAD
Our first balance sheet used placeholder masses for the fuselage, wings and V-tail. Taking volumes from the 3D model gave a 574 g airframe with its own CG at 435 mm, and put the whole aircraft's CG at 411 mm: behind the neutral point, so it would have been unstable.
Moving the wing beats adding weight
Moving the wing 20 mm aft shifted the neutral point 18.2 mm but the CG only about 5 mm. It did the job of about 80 g of nose weight, for no extra mass.
Balance and trim speed move together
Moving the CG aft lowers the stability margin and the trim speed at the same time: 21.2 m/s with the CG at 335 mm, 18.8 m/s at 345 mm. The tail incidence sets the rest.
Check the fit in cross-section
In side view everything fitted. Slicing the round fuselage showed three clashes, and that the battery can only sit on the centreline.
Each tool sees a different aircraft
XFLR5 models the wing and tail with partly laminar flow; OpenFOAM adds the fuselage and assumes turbulent flow everywhere. Lift agreed within 5%, while drag at 3° came out about 60% higher in CFD. Knowing what each tool includes tells us which number to use for what.
Heat is a design load for printed parts
LW-PLA softens at around 55 to 60 °C. The motor sits inside the tail cone and the ESC near the floor, so we are adding vents and printing trays and loaded parts in PETG.
Some choices are mechanical, not about balance
Putting the tail servos at x 520 or x 740 changes the CG by only 2.4 mm, so we will choose between them on pushrod stiffness, access and heat.
Our first CG estimate would have made the aircraft unstable
The CG came out at 411 mm, 47 mm behind the neutral point.
Three components did not fit
The Raspberry Pi, the camera and the motor all clashed with the round fuselage or the narrowing tail cone.
The CAD would not mesh directly for CFD
Some curved surfaces in the STEP export failed in the first meshing tool.
Parallel CFD runs failed at first
Running the solver on two cores clashed with the installed MPI library.
CFD drag disagreed with XFLR5
0.0367 against 0.0227 at 3°.
Our first failsafe settings assumed a radio we do not have
They were written for a pilot with an ExpressLRS radio who would land by hand. Without one, a radio failsafe would trigger at once, the aircraft would refuse to arm, and a return home would end in circling until the battery ran out. Several parameter names did not exist in ArduPlane at all.
The camera speed estimate had its sign reversed
A test against an independent camera model showed forward flight reading as flying backwards. The estimate was switched off by default, so it never reached the autopilot.
The build started late
Airframe printing has not started; the print settings for the foaming LW-PLA still need tuning.
The second parts order slipped
Carbon tube sizes, wire gauge and the arming connector had to come from the CAD first.
- Build the mass model from the CAD on day one, and update it whenever a part changes.
- Fit-check components in cross-section before choosing their positions.
- Order the secondary parts together with the primary set.
- Run a mesh-independence study before trusting drag values.
- Leave room for cooling in every closed compartment.
Progress report
Interim report II covers 24 September to 2 November 2026: what we have done, what went well, what has been difficult, what comes next and how we are tracking against the schedule. We have added the work since then, up to 17 November.
CFD caught a real problem before printing
Running OpenFOAM on Monedula showed it would have been unstable in pitch. We found the cause, changed the design and confirmed the fix with a second run, all before printing anything.
The design is now fully parametric
Monedula is a parametric FreeCAD model. Lengthening the fuselage moved the wing, bay, tail and every joint together, and the clash checks ran again automatically on all 69 parts.
Problems were found on paper
The balance and fit checks found an unstable CG and three component clashes before any part was printed, while they were still cheap to fix.
Main components arrived on schedule
We planned procurement for 6 to 19 October and had all eight primary components in hand on 20 October, so the electronics work is no longer waiting on deliveries.
The aerodynamic design is complete
XFLR5 and OpenFOAM agree on lift and stability, and with the wing moved aft the aircraft has a static margin of about 20%. Aerodynamics is no longer holding up the build.
CAD reached a full-aircraft assembly
Version 4 brings the fuselage, wing, hollow tail with connectors and nose mounts together in one model, which we now use for sectioning, part design and the balance calculation.
We built our own thrust rig
Rather than relying on manufacturer data, we designed and built a stand that measures static thrust for any motor and propeller combination. It will let us check the propulsion choice before flight.
Clear split of work
A shared task sheet with priorities and owners, and a dated plan to 8 December, means each of us knows what is due and when.
Our design tools disagreed
The quick aerodynamic tool we used to size Monedula gave a 14 % static margin; CFD gave −3.4 %. We now check stability with a method that includes downwash and confirm it in CFD.
Joints and hinges are still unproven
The PETG couplers, root ribs and TPU hinges have only been checked in CAD. Bond strength and hinge life need printed test pieces before we trust them in flight.
The build phase started late
Airframe printing has not started yet. LW-PLA is a foaming filament whose weight and strength depend strongly on temperature and flow, so we need test prints to dial it in (5 to 10 November), followed by PETG settings (13 to 16 November).
The second component order slipped
The secondary list has been open since 20 October, and several items still needed sizing from the CAD: carbon tube sizes, wire gauge and the battery arming connector. We will order on 4 November.
Joining printed sections
The wing and fuselage are printed in sections joined with overlapping edges, carbon-filament rivets, bolts and PETG root gaskets. Hole tolerances have to be proven with test pieces before we commit to full parts.
One structural decision is still open
We have not yet decided whether the 12 mm main spar joins at mid-fuselage or runs the full span. It affects transport, assembly and wing removal.
Software work is behind the hardware
Flight-controller programming and datalink research have not started. The internal layout is now fit-checked, but the trays and mounts still need to be modelled. These now sit on the critical path for ground testing.
The thrust rig took longer than expected
We sketched it up to version 5 before building, and it is still being finalised. It has not yet been run with a battery.
From our working plan of 2 November. Printing and assembly of the airframe sections follow as soon as each part model and the print settings are ready. The battery holder and the flight controller mount will follow the tray plan in Inside the airframe.
| Stage | Planned | What happened | Status | Revised |
|---|---|---|---|---|
| Design and analysis | to 5 Oct | Aerodynamics finished on time; balance redone and wing moved on 3 Nov. Detailed part CAD (mounts, connectors, compartments) continues alongside the build. | On track | Detail CAD to 18 Nov |
| Procurement | 6 to 19 Oct | Primary set received 20 Oct. Secondary order delayed while sizes were finalised. | Partly late | Secondary order 4 Nov |
| Build | 20 Oct to 9 Nov | Thrust rig built. Airframe printing not started; print settings still to tune. | About 2 weeks behind | 5 to 30 Nov |
| Testing | 10 to 27 Nov | Not started. | Moved | 14 Nov to 7 Dec |
| Presentation | 28 Nov to 8 Dec | No change. | On track | 28 Nov to 8 Dec |
Our first interim report (23 September) recorded where the project stood before this period.
- CFD analysis in XFLR5 (VLM1 and VLM2); MH32 airfoil selected over RG15 and SD7037.
- Full-aircraft geometry set: 1.40 m span, 0.263 m² wing, aspect ratio 7.46, high wing and V-tail.
- Mass and CG modelling: centre of gravity 0.335 m, static margin 18.5% at 1.58 to 1.60 kg.
- Aileron and ruddervator response evaluated.
- Electronics selected and sourcing links collected; cost target under $500.
- Finalise V-tail geometry and construction details. Done
- Order and receive components. Primary set done
- 3D-print the airframe and wing. Moved to November
- Assemble electronics and test the link. Circuit due 30 Nov
- First ground and flight tests. Thrust test 14 Nov
Timeline, revised 2 November
Five stages working back from the presentation on 8 December 2026. Struck-through dates are the original plan from September.
Design and analysis
- Airfoil selection and XFLR5 analysis of the full aircraft
- OpenFOAM airframe CFD, then a second run with the wing moved 20 mm aft (3 Nov)
- CG from the 3D model and internal layout fit check (3 Nov)
- Full-aircraft CAD assembly V4; part models continue
- SILM Monedula V11: parametric FreeCAD airframe, CFD-checked 14 % static margin, 69 print-ready parts (17 Nov)
- SILM Monedula V11b and its 3D model (18 Nov)
Procurement
- Primary electronics received 20 Oct
- Secondary order (servos, inserts, filament, carbon tubes, connectors) on 4 Nov
Build
- LW-PLA settings 5 to 10 Nov, PETG settings 13 to 16 Nov
- Printing the fuselage and wing sections; joining with rivets, bolts and gaskets
- PETG trays for the battery and electronics
- Electronics circuit finished by 30 Nov
- 4G and WireGuard link added after the core system works
Testing
- Static thrust test 14 Nov (24 Nov at the latest)
- Weighing the printed parts and checking the CG
- Ground tests of control surfaces, link and failsafe after 30 Nov
- First hand-launch as a stretch goal before 8 Dec
- Endurance and range validation after the presentation
Presentation and documentation
- Results summary and final website update
- Presentation day: 8 December 2026
UAV SILM is an ongoing student STEAM project, not a finished aircraft. Every figure on this page (mass, endurance, cost, balance, control response) is a theoretical estimate from CFD analysis and hand calculation, not from flight-test data. The 3D models show our CAD and simulation results, not a built aircraft.
We have not held formal discussions with Kaitseliit or the Estonian Defence Forces; we present the platform as a design study and a longer-term aim toward a working, versatile aircraft.